Power in the datacenter
Electricity is the most critical resource in any server room. Even a one-second outage can corrupt data and take services down for hours. That is why power is designed in layers, each one covering for the previous.
Typical power chain
Utility grid → Transformer → ATS → UPS → PDU → Equipment
│
Generator
(backup)
- ATS (Automatic Transfer Switch): switches between grid and generator automatically.
- UPS: bridges the gap during the transfer (seconds to minutes).
- Generator: keeps the room running through long outages.
UPS: Uninterruptible Power Supplies
| Type | How it works | Transfer time | Use |
|---|---|---|---|
| Offline / Standby | Switches to battery when it detects an outage | 5-12 ms | PCs, non-critical gear |
| Line-Interactive | Regulates voltage without going to battery | 2-4 ms | Small servers, network closets |
| Online / Double conversion | Converts AC→DC→AC continuously | 0 ms | Datacenter (always this one) |
In server rooms, always use online double-conversion UPS units. Zero transfer time, and they filter every power anomaly: spikes, sags, noise and frequency drift.
UPS runtime
Runtime depends on battery capacity and connected load. A datacenter UPS typically gives 5 to 15 minutes — enough for the diesel generator to start, not enough to ride out a long outage on its own.
PDUs: Power Distribution Units
PDUs distribute power inside the rack. They range from a dumb power strip to a remotely controlled, per-outlet metered device:
| Type | Features | Monitoring |
|---|---|---|
| Basic | Power strip with overload protection | None |
| Metered | Total draw shown on a display | Total amps/watts |
| Per-outlet metered | Individual reading per outlet | Per outlet (SNMP) |
| Switched | Remote on/off per outlet | Full + remote control |
| ATS PDU | Dual input with automatic transfer | Full + redundancy |
Recommendation: metered PDUs at minimum. Per-outlet metering tells you which device draws the most — invaluable for capacity planning.
Power redundancy
| Scheme | Description | Tolerance |
|---|---|---|
| N | No redundancy. One failure = outage | None |
| N+1 | One spare unit. Survives 1 failure | Single component |
| 2N | Everything duplicated. Each path carries 100% | Full path failure |
| 2N+1 | Duplicated plus a spare | Path failure + maintenance |
Feed A / Feed B
In a 2N setup, each rack gets two independent power paths, each with its own UPS and PDU:
Feed A ── UPS A ── PDU A ──┐
├── Server (dual PSU)
Feed B ── UPS B ── PDU B ──┘
Servers with redundant power supplies plug into both PDUs. If one entire path fails, the other keeps the server up.
Watts vs VA
- VA (volt-amperes): apparent power — what the UPS is rated to deliver.
- W (watts): real power — what the equipment actually consumes.
- Power factor: the W/VA ratio, typically ~0.9 on modern UPS units and PSUs.
Example: a 10,000 VA UPS with a 0.9 power factor delivers 9,000 W of real power. Always size against watts, not VA.
Capacity planning
- Inventory each device’s draw (nameplate, vendor spec, or a real measurement — nameplate values are usually pessimistic).
- Add up the watts per rack.
- Keep headroom: stay under 80% of the PDU’s rated capacity.
- Balance phases if your feed is three-phase.
- Project growth: reserve capacity for the next equipment you will install.
Power in CreaRack
Each rack in the Rack Editor has a Power Cons. field (in kWh) where you record the rack’s consumption, so the figure lives next to the rack layout instead of in a forgotten spreadsheet. For the UPS side, UPS Monitor tracks your uninterruptible power supplies via SNMP — battery charge, load and runtime — and [[crearack—ups—add-ups-devices]] explains how to discover and add them.
Related
- [[crearack—ups—add-ups-devices]] — add your UPS units to UPS Monitor
- [[crearack—monitoring—que-es-ups]] — what UPS Monitor does
- [[crearack—redes-infra—refrigeracion]] — every watt consumed becomes heat
- [[crearack—redes-infra—cableado]] — physical cabling of the rack
- [[crearack—redes-infra—monitorizacion]] — monitoring the whole infrastructure
- [[crearack-tech—guides—capacity-planning]] — technical capacity planning guide
Véase también
- [[crearack—redes-infra—refrigeracion]]
- [[crearack—redes-infra—cableado]]
- [[crearack—redes-infra—monitorizacion]]
- [[crearack—monitoring—que-es-ups]]
- [[crearack—ups—add-ups-devices]]
- [[crearack-tech—guides—capacity-planning]]